Operator’s Manual Second Edition • First Printing
Fundamentals
The function tests are designed to discover any
malfunctions before the machine is put into service.
The operator must follow the step-by-step
instructions to test all machine functions.
A malfunctioning machine must never be used. If
malfunctions are discovered, the machine must be
tagged and removed from service. Repairs to the
machine may only be made by a qualified service
technician, according to the manufacturer's
specifications.
After repairs are completed, the operator must
perform a pre-operation inspection and function
tests before putting the machine into service.
Do Not Operate Unless:
You learn and practice the principles of safe
machine operation contained in this operator’s
manual.
1 Avoid hazardous situations.
2 Always perform a pre-operation inspection.
3 Always perform the function tests prior
to use.
Know and understand the function tests
before going on to the next section.
4 Inspect the workplace.
5 Only use the machine as it was intended.
Function Tests
1 Position the machine directly below the desired
work area.
2 Connect to the appropriate power source:
DC models: Connect the battery pack.
AC models: Connect to a grounded 15A AC
power supply. Use a 12 gauge / 3.3 mm
2
3-wire grounded extension cord no longer than
50 feet / 13 m.
3 Insert the key and turn to platform control.
4 Pull out the red Emergency Stop button at the
ground controls to the on position.
Result: The power light should come on.
5 Install each outrigger and adjust the leveling
jacks to level the machine. Level the machine
using only the outriggers.
Function Tests